August 1996 Volume 6 Number 8
What If ...
By Tom Wallace
"Hey Lee, what if we pick up two more Target regions out west, can
we start shipping their new-store orders next month?"
"Hey Lee, can we ship the Ford order on the 16th rather than the 23rd?"
"Hey Lee, if that order for GE gets delayed two months waiting for
engineering, what can we pull up to keep the plant busy?"
Sound familiar? If you've ever had a job like Lee's -- in planning, production
control, master scheduling -- you probably know how she feels. How in the
world can Lee respond effectively to those kinds of questions? Answer: with
great difficulty unless ... she has the right kind of tools.
With yesterday's informational tools, Lee's answers would probably be limited
to responses like, "I don't know," "Maybe," and "We'll
give it a try." Notice: "No" is not in this list. And that
points out a fundamental problem that experienced production control people
know only too well: Without the facts, it's impossible to say "no."
Prior to MRP II, people in planning and production control jobs -- the Lee's
of this world -- didn't have a chance. They didn't have the facts and thus
they couldn't say no. Most of the time, they said yes, and as a result,
three other customer orders fell through the crack.
With MRP II, simulation -- the "what-if" capability -- became
possible (but not practical, as we'll see in a moment). The theory was great;
it went like this:
- 1. Copy all of your MRP II-related data onto a separate set of disks,
to be used for simulation.
- 2. Play "what-if" by making the requested changes to the
simulation files.
- 3. Run the master schedule, capacity planning, and/or MRP systems
using the simulation files.
- 4. Evaluate the output and respond -- with facts -- to the person
who asked the question.
This was a breakthrough. For the first time ever, people could play "what-if"
with meaningful results. Prior attempts at simulation came up dry, because
they couldn't capture all of the complex variables present in a manufacturing
company. There are too many variables, too many resources, too many customer
orders. Invariably the person doing the simulation had to make a number
of "simplifying assumptions." Well, one would quickly simplify
one's way out of anything that provided actionable answers to the questions
being posed.
So MRP II filled the void. It offered many advantages: the same data, being
processed by the same program logic, displayed by the same screens and reports,
being used by the same people. This was a quantum leap over the simulation
programs with their simplifying assumptions, their different logic, their
different displays, etc.
MRP II made simulation possible, but for many companies it wasn't practical.
The reason? Time. It simply took too darned long to get answers to the what-if
questions. With MPS/MRP/CRP run times ranging from a number of hours to
several days, MRP was usually run on the weekends. Is it practical to wait
for two or four or six days to give an answer to someone who wants to know
when their order can ship, or can it be shipped earlier, or what happens
if we don't get the order? Is it practical to wait for another whole week
to rerun the simulation if the first pass didn't give you a satisfactory
solution? In a word, no.
And for that reason, simulation has been one of the most underutilized of
all of the MRP II tools. But not for long. Thanks to some very effective
software, it's possible to run your MRP simulations in far less time than
several hours to several days. Would you believe several minutes? Well,
it's being done, by more and more companies every month.
How, you ask, is such a thing possible? Well, conceptually it's very simple:
All the relevant data is loaded from disk into main memory. Then MRP/MRP
II is executed at the speed of light. No more disk seeks, reads, writes,
latency, etc. MRP runs were historically disk bound. The solution: Get rid
of the disk because that's the constraint. I suspect Eli Goldratt would
be proud.
Today, companies like FastMAN Software, Red Pepper Software, Enterprise
Planning Systems and others offer these packages, often referred to as "MRP
accelerators." They're quite good, and if you get one, you'll be in
fine company. I spoke at a FastMAN user group meeting about a year ago,
and some of the companies represented in the room were Hewlett-Packard,
Allison Transmission, Intel, Lexmark, the Trane Company and Microsoft.
With a tool like this, it's possible for people like Lee and her fellow
professionals in the planning and scheduling field to readily answer questions
like "Can we take the new big order?" "Line four just went
down for 10 days, what's going to slip?" "Do we have parts committed
to stock orders that we can shift to take care of _______ (fill in the blank:
Ford, GE, Wal-Mart, HP, Boeing, Office Depot, or whomever).
These kinds of packages are very user-friendly and highly graphical. Some
of them make effective use of artificial intelligence, and can show the
dollar impacts of competing alternatives, resource utilization, etc.
Bear with me for just a moment, while I engage in what might seem to be
some blue sky. Imagine you've implemented sales and operations planning
in your company. Your top management team is meeting once per month to authorize
sales, production, and inventory plans that will harmonize demand and supply.
One of the executives -- the president, or perhaps the CFO -- raises questions:
If we can pull up the new product launch by six weeks, we're sure we can
beat the competition to the market. Can we do it? If so, what other products
might be affected?
You're projecting the S&OP display for this product family onto a large
screen from your PC, which contains the MRP II database for the entire company.
You ask for a brief time-out while you run the MRP II simulation using your
MRP-accelerator software. Within no more than several minutes, you have
answers: Plan A is feasible but will affect product X; Plan B is feasible
but will affect products Y and Z; and Plan C will have the least total cost
but will cause serious stockouts across much of the product line.
The phrase "top management war room" comes to mind. I predict
that within about five years this type of capability will be widespread:
sales and operations planning linked with simulation software running at
the speed of light -- supporting major demand/supply decisions with facts,
not guesses -- in a top management setting. This is not blue sky. It's coming.
What an exciting time to be in this field!
Tom Wallace is an independent consultant based in Cincinnati. He is the
author of Customer Driven Strategy: Winning Through Operational Excellence
(1992) and editor/author of The Instant Access Guide to World Class Manufacturing
(1994). Tom is co-director and a Distinguished Fellow of the Ohio State
University's Center for Excellence in Manufacturing Management.
For more information about this article, input the number
11 in the appropriate place on the Reader