
Intelligent Manufacturing September 1995 Vol. 1
No. 9
Aro Fluid Gets Operations In Synch
Aro Fluid Products (Bryan, Ohio), a manufacturer of pneumatic
handtools, pumps and valves, had a problem at its Angola, Ind.,
manufacturing plant: customer service levels were unsatisfactory and
inventories were out of control. The company's goal was to achieve a
24-hour product turnaround; instead, best-case scenarios still took
anywhere from 10 to 15 days.
That's when Dennis Weaver, Aro's vice president, decided to try the
reengineering concept known as synchronous manufacturing. Pioneered
in the 1980s at General Motors, the original synchronous
manufacturing concept focused only on the shop floor. Al Podzunas, a
one-time GM manager who's now with The MPI Group (Wallingford,
Conn.), has coined a new philosophy he calls Synchronous
Manufacturing 2, which extends the scope to include the web around
the manufacturing floor and incorporate the complete manufacturing
process, including R&D;, product conceptualization, design, order
entry, purchasing, manufacturing, and shipping.
The overall objective is to bring the entire organization together to
serve one goal - customer satisfaction. This is accomplished by
changing the measures, methods and mindset of a company. A company
focuses its energies on increasing throughput (the revenue generated
by sales), while decreasing inventory and operating expenses.
Part of the reason manufacturers get into trouble, according to
Podzunas, is that they focus on labor, rather than the rest of the
picture. Materials, overhead and burden account for about 90% of the
cost of a product. Labor is only 10%, but oftentimes a company will
justify everything on labor.
"Synchronous manufacturing really challenges what has become accepted
as the traditional approach to manufacturing and manufacturing
measurements," Weaver said. "What we were measuring was not driving
us to be better suppliers to our customers. We had a lot of people
working really hard, but we were not making improvements. Our
customer satisfaction records were getting worse and our inventories
were growing dramatically. Employees were frustrated and tired."
One of the first things Aro did was to drastically cut back the
manufacturing batch sizes it was running in the shop. Queue time was
analyzed and cut back dramatically. Moving parts quickly from
operation to operation became a key focal point.
"We had been building to a forecast that was in most cases greater
than, or in some cases, not even what the customer wanted," Weaver
explained. "We were trying to anticipate spikes in incoming orders.
We literally went in and overrode the system and began to manually
release orders rather than waiting until the order was finished."
One major accomplishment, said Weaver, was to identify "where the
true bottlenecks were versus the perceived ones. We had never been
able to do that before. We were able to find the true bottlenecks by
manually doing a process map, which allowed us to predict what our
capacity was and then determine what parts we really wanted to run
across these control points. With this information, buffer stock and
batch sizes were determined."
In order to increase the capacity, Aro personnel videotaped set-ups,
which allowed them insight on increasing efficiency through
workstation improvements, operator training and streamlining set-up
points. "You could clearly see where the fumbles were," Weaver
said.
In one instance, videotaping revealed how awkward it was for
operators to retrieve tooling in the head and cap cell set-up, adding
several hours to the operation. Tool racks were built to incorporate
tooling right at the work site. Blueprints were laminated when it
showed how cumbersome it was to work with them.
"We created a focus factory, where the order comes in and we machine
and assemble the complete part," Weaver explained. From this evolved
a self-directed work force, where workers are cross-trained. A hard
look was taken at the manufacturing areas, as well as the cell
layout. For instance, the old work benches were rectangular and very
difficult to walk around. Parts were not easily retrieved, even in
the work area, and there was more inventory there than required. A
new horseshoe-shaped workbench was designed, with an early parts
retrieval system.
To control inventory, Aro implemented a pull system, which utilizes
cards to notify someone when a carton is depleted. "Now, the system
replenishes as products are needed, not based on a prediction,"
Weaver observed.
Within four months of the launch of the reengineering project,
turnarounds had decreased from 10 days to two days in the critical
cylinder area. Aro has also experienced a significant reduction in
inventory. "A plant-wide house cleaning was held to get rid of what
we didn't need," Weaver said. "We were physically able to take parts
out of the factory by the thousands. We also freed up 20% of our
floor space that can be used as we pursue additional products."
The bottom line is that Aro Fluid Products is so pleased with the
improvement that it is incorporating synchronous manufacturing
techniques into its largest facility, located in Bryan, Ohio, which
comprises more than 400,000 square feet.
Click
here to return to Table of Contents for the Intelligent
Manufacturing September issue.
Intelligent Manufacturing Copyright © 2020 -
Lionheart Publishing Inc. All rights reserved.